Tier-1 manufacturers (LONGi, Trina, Jinko, JA Solar, First Solar, Nextracker, Array Technologies, Sungrow, CATL, BYD) void product warranties when cargo moves on spring-ride trailers, gets chained without dunnage, or gets punctured by short 42-inch warehouse forks.

Demander un Devis ->
TRUCKING.SOLAR // ENGINEERING SPECIFICATION DRAWING SHEET 1 OF 4 DOC. NO. TS-PAT-101 FIG. 1 - 53-FT AIR-RIDE SOLAR TRAILER & OEM SECUREMENT APPARATUS DETAIL A [REF. 20, 22, 24] - PV MODULES 53' Air-Ride Conestoga / Swing-Door Van • Air-Bag Suspension [18]: <2.0G Max Shock • Max 1+1 Stack • Anti-Slip Rubber Mat [24] DETAIL B [REF. 30, 32, 34] - TRACKERS & PILES 48'/53' Flatbed (48,000 lb Payload) • 4"x4" Hardwood Dunnage [32] (3.5" Fork Gap) • 4" Nylon Straps [34] (Zero Chain on Zinc) DETAIL C [REF. 40, 42] - HEAVY SKIDS & BESS Step-Deck / 3-Axle RGN Lowboy • Central Inverters & MV Transformers [40] • UN 3536 Class 9 BESS & Crane Window [42] 11 10 12 RETRACTABLE CONESTOGA BOW SYSTEM [16] (CUTAWAY VIEW) 15 PV PALLET <2.0G 20 22 TORQUE TUBES / H-PILES 30 32 34 PCS / BESS 40 42 18 53'-0" (16.15m) AIR-RIDE DECK • MAX 48,000 LB PAYLOAD [10] Tractor [14] 53' Deck [18] Air-Ride (<2.0G) [20] PV Pallets [32] 4x4 Dunnage [34] 4" Nylon Straps
Wave & Commodity FTL per MW 100 MW Volume Mandatory Trailer Spec Trucking.Solar Field SOP & OEM Warranty Rule
Wave 1: Driven Steel H-Piles
W6x9, W6x12, W6x15 Galvanized
0.8 - 1.2 / MW 80 - 120 FTL 48'/53' Flatbed or Step-Deck (48,000 lb payload, pipe stakes) TS-SOP-002: 4"x4" hardwood dunnage (3.5" fork gap); belly-wrapped 4" nylon straps on short beams; zero bare chains on ASTM A123 zinc coating.
Wave 2: Tracker Torque Tubes
Nextracker, Array, GameChange
0.8 - 1.3 / MW 80 - 130 FTL 48'/53' Flatbed or Conestoga TS-SOP-002: 4"x4" hardwood spacers every 8-10 ft; 4" nylon web straps tensioned <3,500 lbs to prevent thin-wall tube ovalization; 8-ft tarps in winter salt.
Wave 3: Bifacial & Thin-Film PV
LONGi, Trina, Jinko, JA, First Solar
2.5 - 3.0 / MW 250 - 300 FTL 53' Air-Ride Conestoga or Swing-Door Air-Ride Dry Van (>=101" door) TS-SOP-001: Vertical shock <2.0G; max 1+1 pallet stack; anti-slip friction mats; E-track straps <=500 daN; 60" padded telehandler forks; single-layer field storage.
Wave 4: Central Inverters & MV Skids
PCS Skids, Pad-Mount Transformers
0.2 - 0.4 / MW 20 - 40 FTL Air-Ride Step-Deck or 3-Axle RGN Lowboy (35k - 65k lbs) TS-SOP-005: Desiccant + shrink-wrap + 8-ft waterproof tarps; impact/tilt logger (<1.5G); synchronized mobile crane or heavy telehandler slot.
Wave 5: Utility BESS & Substation MPT
Sungrow, CATL, BYD, Megapack
0.5 - 1.0 / MWh 50 - 100+ RGN 3-Axle / 4-Axle RGN Lowboy or Multi-Axle Perimeter Trailer (65k - 150k+ lbs) TS-SOP-005: Carrier PHMSA/FMCSA UN 3536 Class 9 Hazmat endorsement, SOC <=30% certificate, state superload permits, pilot cars, and locked crane rigging window.
TRUCKING.SOLAR FIELD OPERATIONS MANUAL • TS-SOP-001 TO TS-SOP-005

Our 5 Proprietary Solar Freight Standard Operating Procedures

Most freight brokers treat solar farms like retail warehouse freight and hide behind generic checklists. Every load dispatched by Trucking.Solar is governed by five written field SOPs enforced on every Rate Confirmation.

TS-SOP-001 • BIFACIAL & THIN-FILM PV MODULES

SOP-001: Bifacial & Thin-Film Solar Module Transport, Forklift Extraction & Laydown Storage

1. Air-Ride Suspension (<2.0G) & Swing-Door / Conestoga Mandate: All photovoltaic modules (LONGi, Trina, Jinko, JA Solar, Canadian Solar, First Solar) move exclusively on 53-foot Air-Ride Conestogas or 53-foot Air-Ride Swing-Door Dry Vans (>=101" clear door width). Spring-ride trailers and roll-up rear doors are prohibited.
2. Stacking, Spacing & Non-Metallic Strapping: Pallets never exceed 1+1 vertical stacking, maintain a 2-inch clearance from trailer walls, sit on anti-slip rubber friction mats, and are secured with rigid corner V-boards and non-metallic ratchet straps tensioned to <=500 daN.
3. 60-Inch Padded Forks & Single-Layer Field Staging: Site telehandlers must use 48-to-60-inch padded fork blades (extending at least 75%-100% through the pallet stringers) and a >=48-inch backrest. Travel speed with raised glass is capped at 3 mph (5 km/h). Pallets are staged in a single layer only on compacted level ground (<2 deg slope) with 20 inches (500 mm) of aisle clearance.

TS-SOP-002 • TRACKER TORQUE TUBES & DRIVEN H-PILES

SOP-002: Galvanized Tracker Torque Tube & Foundation H-Pile Flatbed Securement

1. 4"x4" Hardwood Dunnage (3.5" Telehandler Fork Gap): Every bundle tier of Nextracker, Array Technologies, or GameChange torque tubes and driven W6 steel H-piles is separated by 4"x4" hardwood dunnage spaced every 8 to 10 feet so site telehandlers can extract bundles cleanly without metal-on-metal scraping.
2. Zero Bare Steel Chains on Hot-Dip Galvanized Zinc (ASTM A123): Loads are secured exclusively with 4-inch nylon web straps and polymer edge protectors. Strap tension on hollow thin-wall torque tubes is capped at <3,500 lbs over dunnage points to prevent tube ovalization. Short foundation H-piles (<16 ft) are belly-wrapped to prevent forward shift under braking.

TS-SOP-003 • PORT FTZ DRAYAGE & CONESTOGA TRANSLOADING

SOP-003: Ocean Container Port Pull, FTZ Buffer Storage & Cross-Dock Transloading

1. Pre-LFD Terminal Pull: Ocean containers at Port of Houston, LA/Long Beach, Savannah, and Norfolk are pulled to bonded/FTZ yards at least 48 hours before Last Free Day (LFD) so shippers pay zero port demurrage or steamship per-diem.
2. Dock-to-Conestoga Conversion: Because rural solar laydown yards lack 48-inch raised concrete loading docks to strip ocean containers from the rear doors, our cross-dock teams extract module pallets using 60-inch padded forks, verify UFLPA serial barcodes, and side-load 53-foot Air-Ride Conestogas for ground-level telehandler offloading at the project site.

TS-SOP-004 • RURAL LAYDOWN GATE, WEATHER HOLD & COUNTY RUA

SOP-004: Rural Laydown Yard GPS Routing, >=20mm Mud Hold & 45-Minute Telehandler Slotting

1. Pre-Dispatch Weather Gate (>=20 mm Rain / >=25 mph Wind): Four hours before gate arrival, Dispatch checks site precipitation and wind telemetry. If 24-hour rain hits >=20 mm (softening uncompacted caliche or black gumbo clay roads) or wind gusts reach >=25 mph (module sail hazard), trucks hold on paved highway staging pads at $0 gate detention.
2. County Road Use Agreement (RUA) & GPS Gate Pin: Drivers never use commercial GPS on the final 5 miles. Every Rate Confirmation specifies the approved County RUA haul route, the exact stabilized construction gate latitude/longitude pin, mandatory PPE (hard hat, Class 2 vest, steel-toe boots, long pants), and a reserved 45-minute telehandler window (2 hours free time).

TS-SOP-005 • UN 3536 BESS HEAVY HAUL & OS&D CLAIM PROTOCOL

SOP-005: 3-Axle/4-Axle RGN Lowboy (UN 3536 BESS & MPT) & OS&D Exception Protocol

1. UN 3536 Class 9 BESS & Transformer Rigging Sync: Enclosures between 65,000 and 150,000+ lbs move on 3-axle/4-axle RGN lowboys or multi-axle perimeter trailers operated by Hazmat-endorsed carriers (UN 3536 Class 9 placards, ERG Guide 147, SOC <=30% certificate, state superload permits, and pilot cars) synchronized to the hour with the jobsite mobile crane.
2. In-Situ OS&D Photo & BOL Protocol: If a seal break, red ShockWatch/TiltWatch tube, or transit damage is found at arrival, the pallet is photographed in place on the trailer deck before forks touch it (4 photos: unit/plate, ShockWatch/damage, OEM serial tag, and strap/dunnage layout), noted explicitly on the BOL with both driver and superintendent signatures, and transmitted to dispatch@trucking.solar before the truck leaves the gate.

BUREAU DE SOUMISSIONS • SPOT • VOIES DEDIEES • APPELS D'OFFRES RFP

Demander une Soumission de Fret Solaire ou Soumettre un Appel d'Offres

Chaque expedition est chiffree sur mesure : d'un chargement spot urgent a plus de 600 camions complets pour un parc solaire de 150 MW. Recevez un prix ferme adapte a votre corridor.

  • TS-SOP-001 (PV Modules): 53' Air-Ride Conestoga or Swing-Door Van (<2.0G shock limit, max 1+1 stack, anti-slip mats).
  • TS-SOP-002 (Trackers & H-Piles): 48'/53' Flatbed (48,000 lb payload, 4"x4" hardwood dunnage with 3.5" fork gap, 4" nylon straps, zero chains on galvanized zinc).
  • TS-SOP-004 (Laydown Gate & Weather Hold): Verified rural gate GPS pin, 45-minute telehandler slot, and >=20mm rain / >=25 mph wind hold protection.
  • TS-SOP-005 (Heavy-Haul & BESS): Air-Ride Step-Deck and 3-Axle/4-Axle RGN Lowboy with UN 3536 Class 9 Hazmat endorsement and crane window sync.